The Ras Al Khaimah casino forms part of Wynn Al Marjan Island on Al Marjan Island, but it was not open to the public on 10 August 2026. Wynn's latest published guidance puts the resort's guest opening in September 2027.

Status at a glance

This panel distinguishes finished milestones from planned work and attaches a date to each time-sensitive figure. Since the opening and operating details may move, every row uses the latest official reference available.

EntryVerified statusSource date
Resort statusUnder construction and not open for visits10 August 2026
Opening dateSeptember 2027Wynn results, 4 August 2026
LicenceIsland 3 AMI FZ-LLC, trading as Wynn Al Marjan, is listed by GCGRACurrent GCGRA register
Tower70 floors, with a final planned height of 352 metres above sea levelCurrent resort website
Accommodation inventoryAll 1,530 units structurally complete2 February 2026
Gaming area225,000 sq ft, about 20,900 sqmWynn 2025 annual filing, March 2026

A construction site cannot accept bookings for rooms, restaurants or the gaming floor. Wynn currently provides an email update form, though submitting it does not reserve a room or grant admission.

What is Wynn Al Marjan Island?

A full resort rather than a separate casino

Wynn Al Marjan Island will be Wynn's first integrated resort in the Middle East and North Africa, and its developers call it the UAE's first. The single destination is planned to bring together a hotel, licensed gaming facility, dining, entertainment, retail, spa, beach, marina and events centre.

Site and development partners

Facing the Arabian Gulf, the project occupies more than 60 hectares on Al Marjan Island in Ras Al Khaimah. It is a joint venture between entities linked to Wynn Resorts, Marjan and RAK Hospitality Holding; the gaming licence register names Island 3 AMI FZ-LLC.

Why the resort format matters

This is more than a gaming floor beside a hotel. Published plans and updates focus largely on accommodation, restaurants, beach facilities, events and entertainment, while Wynn has not yet set out the detailed game mix.

Wynn Al Marjan is scheduled for September 2027

The newest official date

Wynn stated in its second quarter results on 4 August 2026 that guests are due to enter the resort in September 2027. That is the latest named month, replacing references that say only 2027, first quarter 2027 or spring 2027.

How the earlier target moved

Earlier investor updates pointed to the first quarter of 2027. After Wynn mentioned a modest delay in May 2026 without yet quantifying it, the August release supplied the revised guidance: September 2027.

How firm is September?

A results release carries more weight than a property listing or travel blog, yet it remains forward-looking guidance while the resort is being fitted out. Check the official resort website and Wynn investor releases before paying for a non-refundable trip.

From project announcement to planned opening

The milestones that changed its status

Reading the announcements chronologically keeps an earlier target separate from the current one. The sequence follows the Ras Al Khaimah casino from proposal through licensing and construction to its named opening month.

Recorded dateMilestone reachedMeaning
25 January 2022Joint project announced for Al Marjan IslandThe concept began with preliminary scope and timing
4 October 2024Wynn announced receipt of the commercial gaming facility operator licenceThe project became the UAE's first licensed commercial gaming facility
25 November 2025A site ceremony marked the 70-floor hotel tower reaching its topThe main tower hit a visible construction milestone
December 2025Wynn's later updates recorded structural concrete completionWork shifted further into the crown, facade and interior phases
2 February 2026Facade reached 83%, all accommodation units were structurally complete and Wynn Bridge reached 48%This remains the newest detailed construction percentage release
11 March 2026Construction resumed after a short pauseThis was a status update, not an opening or cancellation notice
29 June 2026Wynn announced an original theatre production with PunchdrunkThe opening entertainment programme gained a confirmed headline show
15 July 2026Wynn's investor presentation showed extensive interior work in progressThe latest visual snapshot verified the fit-out phase was active
4 August 2026September 2027 was named for opening the doorsThis is the current official date to use for planning

Reading the November and December entries

A Wynn project story places the 70-floor ceremony on 25 November 2025, whereas later corporate updates place the structural concrete milestone in December 2025. The timeline keeps November for the ceremony and December for the later construction record instead of collapsing the two references.

Construction progress through August 2026

Tower and facade work

In its 2 February 2026 release, Wynn reported structural concrete complete through the roof of level 71 and 21,852 of 26,471 facade panels installed, or 83%. The guest website still calls it a 70-floor tower. Wynn has published varying interim height measurements, while the lasting target is 352 metres above sea level once the spire is fitted, so the descriptions remain separate.

Interiors and lower buildings

Lift and escalator installation was advancing, alongside mechanical, electrical and finishing work throughout the guest inventory. Concrete and structural steel for the low-rise buildings had reached 99%, but that percentage does not make those spaces guest-ready.

Wynn Bridge

Wynn Bridge, measuring 548 metres, is intended to link the resort via Wynn Boulevard with E311 and E611. On 2 February 2026 it was 48% complete: piling was finished and nine of ten bridge-column pile caps were in place, with Wynn targeting completion in late 2026.

What August adds

Wynn's August results described rapid construction progress, and its second quarter presentation showed extensive interior work on 15 July 2026. Neither source added a facade or bridge percentage, so the February figures remain dated rather than being extended through speculation.

Gaming floor area and resort scale

The direct company figure

Wynn's 2025 annual report, filed in March 2026, records a gaming area of 225,000 sq ft. That is about 20,900 sqm, and this guide uses it because the figure comes from the latest direct corporate filing.

Why 18,500 sqm also appears

Older property and news reports, including current search results, often give an approximate 18,500 sqm gaming floor. Wynn has not explained whether the measurements cover different spaces, so 18,500 sqm remains an older estimate and is not combined with the newer figure.

MeasureFigure shownHow to interpret it
Gaming area225,000 sq ft, about 20,900 sqmLatest figure in Wynn's annual filing
Older figure still repeated onlineAbout 18,500 sqmLegacy estimate, not the current lead figure
Development siteMore than 60 hectaresThe whole integrated resort, not only the gaming floor
Hotel tower70 floorsCurrent guest-facing description
Structure in the February update299 metres through the level 71 roofA dated construction measurement, not final height
Planned height with spire352 metres above sea levelFinal architectural target on the resort website

What floor area cannot tell you

A floor measurement says nothing about the number of tables or slots, the game mix, or the split between general and private rooms. Wynn had not published those details by 10 August 2026, so a precise inventory requires a newer operator source.

Guest rooms, suites and residences

The breakdown of 1,530 accommodation units

Wynn's February construction update reported structural completion for all 1,530 accommodation units, although interior fit-out continued. The categories below remain within that total, preventing the apartments, townhomes and estates from being counted again.

CategoryNumberPublished detail
Resort rooms1,217Rooms and suites in the main Resort Tower
Enclave suites297A hotel within a hotel on the upper floors
Royal Apartments2Two apartments at the top of the tower
Garden Townhomes4Standalone garden accommodation in the resort plan
Marina Estates10Residences beside the marina
Total1,530Current announced guest inventory

Inside the Enclave concept

Enclave is Wynn's hotel-within-a-hotel arrangement on the upper floors, with a dedicated entrance, arrival area and lifts. It is centred on suites and a separate service setting, while rates, packages and the reservation opening date remain unannounced.

Why older pages list 1,542 rooms

Older Wynn releases introduced the 1,542 figure, which competitors still repeat. The February 2026 construction release and current resort materials give a complete category breakdown totaling 1,530, the figure used here.

Dining, theatre, shopping and art

Twenty-two dining and drinking venues

The current resort website lists plans for 22 restaurants, bars and lounges, as well as a daytime beach club serving guests and visitors. Wynn has identified a French-American steakhouse by Alain Ducasse and another Delilah supper club, but restaurant bookings were not open at this update.

The Showroom production by Punchdrunk

Wynn announced an original Punchdrunk production on 29 June 2026 for the resort's debut. Once bookings begin, guests are expected to choose between a seated upstairs performance and a roaming immersive route downstairs and backstage; show dates and prices remain unreleased.

Shopping and the art collection

The plans call for a naturally lit shopping parterre for luxury brands, although Wynn has not issued the complete shop list. Art will appear across public areas and guest rooms, with announced highlights such as Jeff Koons' 11-metre Tulips and historic and contemporary works by regional and international artists.

Beach, pools, spa and marina facilities

The waterfront plan

The resort plan provides for 420 metres of private white-sand beach and a deep-water marina for large yachts. It also includes a daytime beach club, though day-pass and non-guest access rules have not been published.

Pools and wellness facilities

Wynn lists 12 pools, cabanas and landscaped areas, plus a five-star spa, salon and fitness centre. Treatment prices, operating hours and pool admission conditions are still unavailable, leaving them out of any reliable visit budget.

Services for families

The official amenities list pairs a kids' club with outdoor recreation, indicating that the resort's non-gaming spaces are designed to welcome families too. Ages, fees and supervision arrangements are not yet published, so childcare planning should wait for the guest policy.

Coral Court events and meetings

A 7,708 sqm events centre

Coral Court will serve as the resort's events and celebrations centre, covering a published 7,708 sqm. Its plan includes six reconfigurable meeting rooms, separate salons for brides and grooms, and private prayer rooms for men and women.

The column-free Grand Ballroom

The Grand Ballroom spans 2,633 sqm, is column-free and looks over the marina. Organisers can use the measurement to compare venues, but it does not set capacity because tables, stages, aisles and production equipment change the seating plan.

Information to request before booking

By 10 August 2026, Wynn had not released venue packages, prices or minimum spends. When sales open, ask for written capacity details and a quote covering production, catering, cancellation and accessibility rather than deriving attendance from floor area.

Getting to the resort on Al Marjan Island

Airport options and the Dubai drive

Al Marjan Island in Ras Al Khaimah, rather than Dubai, is the resort's location. Wynn's website estimates about 15 minutes by car from Ras Al Khaimah International Airport, while a 2025 Wynn financing release put the Dubai International Airport drive at roughly 50 minutes.

Origin or routePublished detailPlanning note
Ras Al Khaimah International AirportAbout 15 minutes by car on the resort websiteReview the journey time on arrival day because traffic changes
Dubai International AirportAbout 50 minutes in Wynn's 2025 release, with the resort less than 50 miles awayAdd baggage and traffic time rather than treating the estimate as a guarantee
Wynn BridgePlanned link through Wynn Boulevard to E311 and E611Late 2026 was the completion target, so verify that the route is open
Resort shuttleNo operating timetable or fare publishedDo not plan around a service the operator has not announced
Parking and valetFinal operating details not publishedCheck arrival instructions when reservations open

What Wynn Bridge is meant to do

The 548-metre bridge should give the resort a more direct connection to the wider road network, but the latest detailed release still treated it as construction. Wait for a completion announcement or a current mapping service to verify the route before treating it as open.

What to check on arrival day

Once bookings open, confirm the final drop-off because the hotel, events centre and marina may have separate entrances. Build in spare time and pay for a transfer only when it appears in written reservation verification.

  • Confirm the airport, terminal and flight number before arranging transport.
  • Check E311, E611 and Wynn Bridge traffic on the travel date.
  • Ask the hotel for the entrance name and baggage drop-off location.
  • Confirm parking, valet and accessible arrival options during booking.

GCGRA licensing and the facility operator

The licensee's exact legal name

The GCGRA licensee register names Island 3 AMI FZ-LLC, trading as Wynn Al Marjan, among land-based gaming facilities. On 4 October 2024, Wynn announced that the project entity had received the UAE's first commercial gaming facility operator licence.

What this licence proves

The register verifys a GCGRA licence for this named land-based facility. It lists The Game LLC separately as the UAE Lottery operator, illustrating the distinction between land-based facilities and lottery products. Wynn Al Marjan is set to become the first licensed casino in the Gulf Cooperation Council when it opens; wider regulation is discussed on our UAE gambling laws page.

What should appear before opening

Before players are admitted, Wynn should publish the gaming floor's final age, identity, admission, responsible gaming and complaints arrangements. Rules from other Wynn properties do not apply here unless this resort publishes them.

Details Wynn has not announced

What was still unknown on 10 August 2026

Resort operating details often shift in the months before opening. Separating unknowns from verified figures helps prevent an email registration, design image or third-party offer from being read as a booking or operational commitment.

DetailStatus as of 10 August 2026Recommended action
Hotel bookings and room ratesReservation date and prices not announcedSubscribe to official updates and wait for Wynn's booking engine
Restaurant reservationsNot open on Wynn's dining pageAvoid paying an unverified intermediary for a table
Casino game listTable, machine and title counts not publishedLook for the operator's gaming information
Betting limitsMinimum and maximum stakes not publishedDo not substitute limits from Wynn Las Vegas
Age, ID and admission chargesFinal Wynn conditions not publishedCheck Wynn and GCGRA before making the trip
Dress code and opening hoursNot publishedReview the guest guide when it appears
Shuttle, parking and valetNo operating timetable or pricing publishedAsk for verification with the hotel booking
Theatre ticketsInterest registration available, schedule and prices incompleteDo not treat registration as a ticket

An email sign-up does not reserve anything

Wynn's website collects email addresses and interests for news and early updates. It does not hold a room, restaurant or theatre seat, nor does it set a price or priority without separate booking verification.

A practical three-step source check

Use the resort website first, compare the licence with the GCGRA register, then compare the opening date with Wynn's newest investor release. When an official channel omits a detail, record it as unannounced rather than borrowing another resort's policy.

  1. Check the date on the page or release, not just the headline.
  2. Keep a construction target separate from a completed milestone.
  3. Retain booking verification and cancellation terms after sales begin.

Plan a responsible visit after opening

Set the age and budget limits first

This page and its gaming content are intended for adults aged 18 and over. GCGRA advertising standards classify anyone below 21 as underage for commercial gaming other than lottery. Wynn had not issued final gaming-floor identity and admission rules by this update, so check them before travelling and do not treat hotel access as access to every resort area.

A worked UAE dirham budget

For illustration, imagine a future one-day entertainment budget of 800 United Arab Emirates dirhams (AED), not a Wynn price. Reserve AED 500 for transport, food and contingency, and set AED 300 as the firm gaming ceiling whatever the outcome.

Rules for stopping

Choose the spending limit and finishing time before entering the gaming area, leaving extra cards and funds outside the plan. Once either limit is reached, leave instead of transferring contingency money to a new stake or chasing a loss.

  • Keep rent, bills and borrowed funds out of play.
  • Never increase a stake to recover the previous round.
  • Set an end-of-session alarm and take breaks.
  • Stay away from the ATM after reaching the planned limit.
  • If Wynn offers cooling-off or self-exclusion tools and you need one, use it.

When support is needed

Stop when gaming brings hidden spending, borrowing, anxiety, or neglect of work and relationships. Our responsible gambling guide covers warning signs, a stopping plan and support options in more detail.

Questions about Wynn Al Marjan answered

Check these points before travelling

The answers below reflect published information available on 10 August 2026. Recheck the opening date and entry terms when reservations begin because future operating details may change.

Source-based answers

No. Construction is still under way, and Wynn said on 4 August 2026 that guest arrivals are planned to begin in September 2027.